Re: Punchlist #52 - LSJ MC Kitchen Kick Plate
this is a priority for jee can you please advise when work will begin and be completed and then update on smart sheet
thank you
Richard Kahn
HBRK Associates
Inc.
575 Lexington
Avenue, 4th Floor
New York, NY
10022
We have 2 carpenters on tiki tile and two carpenters installing 5 Palms windows. The windows should be complete tomorrow, but JE sent instruction today to also build a door and some panels at 5 Palms. Once complete, will shift to Kickplates.
ok. thank you So realistically, kick plates beginning of next week? or when? considering the new request?
I would say maybe two weeks out to start, then two weeks to finish (MC Kitchen, FPP Kitchen, Tiki Kitchen - in that order) Stephanie Remington LSJE, LLC
ok, thanks...update the SmartSheet with the dates when you have a moment
The kick plate is just Strips of wood with formica on it. Sylvester can do that in no time
I'll try to get it done tomorrow with Sylvester or one of the other carpenters.
Ann R.
That is great news! Thx Anna