Photos - September 11, 2015
Greetings Sir,
September 11 photos for your review and comments:
MBR flooring - sanding #3 completed and epoxy applied - Pokey on site 9/13 for sanding #4
Pebble Beach - clean up continues - Danny received your directive for a smooth finish - he is to calculate the
amount of yards of concrete needed and get a quote from Heavy Materials and the pump truck company - Danny says the pump trucks should be able to get all the way down to the beach
Stone wall along road to Info Center - in progress
Waterfall cistern - slab poured today - block laying on 9/14
Gym A/C shed - painting completed
Dining Terrace ceiling fans changed out from the rusty ones
Fuel Depots - RanVar came out to calibrate the fuel depots and uncovered severe rusting and 4 leaks - 3 in the diesel and 1 in the premium gas depot - they will make repairs, but are strongly recommending both depots be changed within the year - they are preparing the quote for the replacement - in the meanwhile they will complete the repairs and cleaning needed for continued function and the upcoming Terminal Facility License inspection
EFTA00846509
Kitchen cabinetry in island - repairs being done on the cabinets in the island Attached also for your review and comments is the Punch List updated 9/11/15. Respectfully submitted, Daphne and Anna
EFTA00846510