Im working to get Jay to send me hi= tile guy for a week starting this Wednesday, waiting on the confirmation.=C2 I will have them starting on the steps and cracked coral stone aroun= your areas then moving on to Cabana 3-4 bathrooms (as long as we have no =ssues with fixture install). They will all be done before you arrive=again.
Also mentioned to me abo=t hiring 3-4 guys for a concrete forming group, do you still want to proce=d with that? I have a few guys in mind but I think we should hire th=m at the same time as the car-mix shows up to the island. The second=part of that is do we want to hire them under LSJ or under my EIN (KR Buil=ers LLC) since I am technically a sub-contractor of Jay. Please let me kno= what you think. Thank you!
Very Respectful=y,
Kyle Reavis
tile , even if luciano. but get it done . =AO ok re car nix