Re: Photographs - March 11, 2011
Greetings Mr= Epstein,
March 11 photographs for your review and comments:
Kitchen banquette
Kitchen drawer
Pool main compound
Flagpole pool
Library floor stain samples
Globe
office trim painting progress - first of two coats applied=/div>
Steps
Little office - Gary Moses is laying out the electrical plan for Gary =erney's review - no photographs for March 11.
Entry - there has been no activity at the entry since the March 5 phot=graphs - I will send many pictures of the boulder basket this week as requ=sted.
Landscaping - the ficus and jasmine hedges off the back terrace and =long the steps leading to the master were planted March 9 and photograph=d March 10. Landscaping maintenance in progress today - no photog=aphs for March 11.
Respectfully submitted,
Daphne
the stain MUST BE SHOWN IN THE LIBRARY WITH CABINETS AND CEILING IN THE SAM= PHOTO