Pokey was scheduled to be completed 8/21
he had to replace plywood subfloor/lost two days
he was out three working days last week
he has no helpers as they are on other jobs
progress is slow - he cannot be pushed
words came with a tongue on end - old floor did not have. he has to cut off on some - time consuming.
based on rate he is going finish floor - new projected date 8/28
then there is putting room back together and cleaning - 1 day
bathroom needs mold remediation including rug and replacing pad - Anna needs to schedule for 8/31
with ReefCo once all items are out of bathroom or schedule now to move date up.
• New target day - 9/2/15 (as long as pokey doesn't disappear again)
When will my room be ready??!!
I am not interested in why. Sorry, today is the 18 and finish was 21. In the future I would appreciate notice.