Thank you for coming by to review windows
Please advise when your bid may be ready for review and discussion
Thank you
Thank you for coming by to review windows
Please advise when your bid may be ready for review and discussion
Thank you
Thank you for your time, Please see the attached proposal, please review and call with any questions or concerns.
I look forward to your reply.
Proposal SAF-Q16.040 -A = Partial Replacement Proposal Full Replacement Proposal to be sent in the next e-mail.
Kind Regards,
Scott Fullwood
Coastal Windows and Doors, LLC.
Sent from my iPhone
Per our Conversation please see the attached proposals and links.
Thank you for your time.
http://bildau.de/new/?page_id=456&lang=en
Kind regards,
Scott Fullwood
Coastal Windows and Doors, LLC.
8300 Resource Drive
West Palm Beach, FL 33404
please advise when you are free to review attached thank you
Richard Kahn
HBRK Associates Inc.
New York, NY 10022
I discounted the total by $2,247.80 Total remaining at $92,187.75 I look forward to your reply and hope we can do business together.
Kind Regards,
Scott Fullwood
Coastal Windows and Doors, LLC.
8300 Resource Drive
West Palm Beach, FL 33404
Please see the attached for your approval. Questions or concerns please call or reply.
Kind Regards,
Scott Fullwood
Coastal Windows and Doors, LLC.
8300 Resource Drive
West Palm Beach, FL 33404
i know you approved already however i wanted to send you all facts that i am aware of so there are no surprises
- Window Functionality
currently you have horizontal rollers (see picture 1 below) unfortunately horizontal rollers are no longer made in wood mahogany
Hartman (original bid from dan labonte and vendor that supplied LSJ) proposed a wood mahogany outswing casement window (see picture 2 below)
bid was 22,250 before other work, permit fees and gc fees -> projected cost 298,000
Coastal proposed a wood mahogany tilt and turn window (see pictures 3 & 4 below) Proposal was for windows to tilt and turn in (picture 3) however if you do not like they can tilt and turn out (picture 4)
Scott from Coastal believes the tilt and turn in is a better design negotiated bid is 90,000 before other work and permit fees -> projected cost 125,000
- Next steps
a) wire requested is 50% of materials and permit fees or 32,727.83 along with signed contract
b) shop drawings will be ready in 2 weeks for your review
c) file for permit
d) order windows (12-14 weeks)
e) install windows (2-3 weeks)
Projected completion date November 1 - 15
- Other contractor work required
Drywall / Stucco repairs
Repaint trim and walls around windows
Protection
Remove any window treatments and put back when completed
Remove any art and furniture
Alarming of new windows
Removal and reinstall of storm shutters
- Work to be provided by Coastal windows
Removal of old and installation of new windows
Buckling / Waterproofing
Rain simulation testing
Scaffolding
Portajon
- Other Notes
a) Windows will be staged in garage bay at 358 el brillo
b) Windows (interior and exterior) will receive 2 coats of primer and 2 coats of topcoat
c) Hardware for Multipoint lock system (medco or tricoat) - you will choose at time of shop drawings (satin nickel, oil rubbed finish)
d) Framing currently is 2.5 inches thick and new window frames will be 3 inches thick
e) Currently we do not have screens and they are not proposed in bid
f) Warranty - 1 year on installation and 10 years from manufacturer for failure in workmanship
g) House to be painted after windows are installed (3-4 weeks)
Please advise if ok to proceed
Thank you