Re: 9 East 71st - Stair Hall & Master Bathtub Alcove Proposal 4-12-18.pdf
The bathtub is an allowance its only in France and there is a=long lead time of 10 weeks. Maybe we can ask the designer to come up with =ne more accessible
Painting number includes all the antiquing of the gold trim on 1st and 2nd =loors skimming the walls after they take off the trim and repainting all S=eetrock areas on 1st and 2nd stair halls and base painting bathroom ceilin=
The site maintenance is the protection price for entry foyer, stair hall an= upstairs it was the only number i had to negotiate harder but its a lot o= work
They are saying 8 weeks to give themselves a buffer there is definitely 2 w=eks in protecting and putting up and taking down scaffold
I will make sure it gets done in 6
Everything is detailed in attachment
Please let me know if you want to discuss
Thanks
Sent from my iPad
does it include the scaffold in the bathroom? 4,>=A0 not sure why so heavy in supervisoni it is only painters.
Y=s includes scaffolding in bathroom and priming bathroom ceiling =br>
I can beat them up on supervision when you are ready to rele=se
do i understand that to paint two walls in the entry hall and prime=the ceiling in the bath is 100k
The walls in the stairway are all being skimcoate= and leveled to level 5 the take the paint
What does that mean sorry=C2.