Hi Mike. Will the welder come today? Has he confirmed? You had said he would come Wed or Thurs. let us know. Thanks.
Sent from my iPhone
Hi. Yesterday morning he called to yet again to reschedule for Thursday or Friday. Once he starts hanging the gates the work will take two to three days. Tomorrow the second beach well for the desal unit on
GSJ will be going in along with the brine outflow well. That work will be two to three days.
Ok. Thanks for update.
Sent from my iPhone
michael please update punchlist with welder timing to arrive and duration to complete gates..
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York, NY 10022
Mike, did the welder show up today I hope? or does anyone know? (this was one of Jeffrey's questions yesterday morning...)