RE: AYH - security and elevator update
relayed
-----Original Message-----
From: J. Epstein [mailto:jeeproject@yahoo.com]
Sent: Tuesday, March 25, 2008 1:03 PM
To: Lesley Groff
Subject: Re: AYH - security and elevator update
thanks
----- Original Message ----
From: Lesley Groff lesley@nysgllc.com
To: J. Epstein jeeproject@yahoo.com
Sent: Tuesday, March 25, 2008 7:49:13 AM
Subject: FW: AYH - security and elevator update
-----Original Message-----
From: Farkas, Andrew L. [mailto:afarkas@islecap.com]
Sent: Tuesday, March 25, 2008 10:43 AM
To: Lesley Groff
Subject: Fw: AYH - security and elevator update
Pls give to JE. It is an update on capital work at American Yacht
Harbor.
----- Original Message -----
From: Garner, Charles
To: Farkas, Andrew L.
Sent: Tue Mar 25 10:34:14 2008
Subject: Fw: AYH - security and elevator update
Fyi. Please let me know if you have questions.
Thanks.
Charles Garner
Island Capital
Tel: 212/705-5087
Fax: 212/705-5001
Email: cgarner@islecap.com
Sent from my BlackBerry Wireless Handheld with apologies for typos
caused by clumsy thumbs.
----- Original Message -----
From: Seiersen, Catherine
To: Garner, Charles
Sent: Tue Mar 25 09:48:15 2008
Subject: AYH - security and elevator update
Fyi -
From: Petty, Chris
Sent: Tuesday, March 25, 2008 9:45 AM
To: Seiersen, Catherine; chris@ayhmarina.biz; Roth, Wesley
Cc: Criswell, Ken; Olszewski, Mike
Subject: RE: Security
Hello Catherine,
- Elevator - The interior of the elevator has been completely
stripped of 15 years paint. The floor covering in the interior of the
elevator has been removed. The exterior metal framing and door on the
second floor have been stripped of 15 years paint. The back portion of
the interior of the elevator has been sprayed with the first coating of
an automotive based paint and is currently drying. Rusted and or dented
portions of the exterior 2nd floor metal frame have been faired smooth
with bondo and sanded. The exterior metal framing and door on the
second floor have been sprayed with the first coating of an automotive
based paint and currently drying. The third floor exterior metal
framing and door have been faired with bondo, sanded smooth and the
first coating of paint has been applied and is drying. The finished
product for the walls of the elevator, exterior doors and metal framing
will be a high gloss automotive finish. Stainless steel
paneling is being cut to cover the fiberboard panels at the front of
the elevator. The floor covering will be replaced with a paver brick
consistent with the exterior of the property. The pavers will be less
subject to cracking or chipping under the load of dollies and hand
trucks. We anticipate completion of the project by the end of this
week.
- Security fencing - We have been in contact with the CZM this
morning (3/25). They are currently working on our proposal and we
expect a response from them today. Once CZM approval is received, we
will immediately remit a deposit to begin work on the fencing.
Please let me know if you have additional questions.
Thanks,
Chris
-----Original Message-----
From: Seiersen, Catherine [mailto:cseiersen@igymarinas.com]
Sent: Monday, March 24, 2008 8:02 PM
To: chris@ayhmarina.biz; Roth, Wesley
Cc: Criswell, Ken; Olszewski, Mike
Subject: Security
With the ops meeting tomorrow, would you please let us know the status
of the security upgrades, as well as the elevator and any other items
that might be pertinent first thing in the morning? I am sure we will
be asked.
The information contained in this message and any attachment to it may
be privileged, confidential or otherwise protected from disclosure. If
you are not the intended recipient, you are hereby notified that any
dissemination, distribution or copying of this communication is strictly
prohibited. If you have received this communication in error, please
notify the sender immediately by replying to the message and please
delete it from your system. Please also note that any views or opinions
presented in this email are solely those of the author and do not
necessarily represent those of the company.