FLORIDAN AQUIFER PLANT COSTS
Cost Estimate for 10 mgd Floridan Plant
Raw Water Wells & Piping 13,500,000
Pretreatment System 5,000,000
Membrane Building w/LPRO system 19,000,000
Chemical Feed Systems 2,000,000
Yard Piping 1,500,000
Clearwell 1,200,000
Transfer Pump Station 1,000,000
High Service Pump Station 2,100,000
Ground Storage Tanks 3,900,000
Dedicated Water Transmission Piping 6,000,000 64,200,000 1,284,000 1,926,000 1,284,000
pwca CS Boed CO Eoee CO Been CF Deed OD
Conceptual Cost General Requirements (2%) Construction Mark-up (3%) Mobilization (2%) Contingency (10%) 6,420,000 Engineering and Other Non-Construction Costs 5,136,000 TOTAL CONCEPTUAL COST §$ 80,250,000
AAA HA 6 aes
Assumes no additional cost for land.