Cost Estimate for 10 mgd Desalination Plant

Site Work 3,000,000

Raw Water Intake, Pumping, Piping, and Fine Screens 12,000,000

Coagulation, Flocculation, Clarification 3,900,000

Pretreatment Transfer Pumping 700,000

Microfiltration : 22,000,000

Ultraviolet Light $ 4,100,000

Chemical Treatment $ 1,600,000

Reverse Osmosis Membrane System $ 48,600,000

Post Treatment Chemical Systems 2,300,000

Ground Storage Tanks 3,900,000

High Service Pumping 2,100,000

Residuals Handling 10,300,000

Brine Disposal Injection Well 6, 000, 000 Conceptual Cost $ 128,400,000

General Requirements (2%) $ 2,568,000 Construction Mark-up (3%) $ 3,852,000 Mobilization (2%) $ 2,568,000 Contingency (10%) $ 12,840,000 Engineering and Other Non-Construction Costs (8%) $ 10,272,000 TOTAL CONCEPTUAL COST §$ 160,500,000

Assumes plant on City property & no additional cost for land.