open_in_new View original source

To: jeevacationQgmail.com[jeevacation gmail.com]; Jeffrey Epsteinueevacation@gmail.com] Cc: Emad Hanna From: Gary Kerney Sent: Wed 7/27/2011 6:43:48 PM Subject: walls FYI Status of Island Wall construction and costs, target to be all completed by the end of sept. All our people are working on flagpole site expect to be done 1st sept. move to road turn around an walls at master done end of sept. Sub Russ $28 sq.ft.(Premium on dregee of dificulty) finished collumn wall working Sea wall done 3rd of Aug move to upper terrace done 2end week sept. Sub Tyson $25 for unpoint $35 pointed buildings Cottage exterior and assioated base end of aug Planter wall mid sept little bath exterior mid sept Sub Tyson 2end crew $25 hell wall done end of aug. All the subs need manual checks as we measure their work. EFTA_R1_00478690 EFTA01987449