To: Jeffrey epstein[jeevacation©gmail.com] From: Gary Kerney Sent: Tue 8/9/2011 1:27:01 PM Subject: RE: 5 palms not yet, need following to layout slab I need new engineering of the foundation footings and steel supporting the high walls comfirmation on the door openings size and locations confirmation on size 16x32 From: Jeffrey epstein [mailtoleevacation@gmail.com] Sent: Tue 8/9/2011 8:44 AM To: Gary Kerney Subject: Re: 5 palms Have we done anything to site? Sorry for all the typos .Sent from my iPhonc On Aug 8, 2011, at 10:07 PM, "Gary Kerney" wrote: latest plan attached ,the changes inside prompt revisiting the concept ceiling apply canvas install big bookcase any doors on east or west walls? what is the roof copy flagpole building? plaster exterior? image for doors?transom? I'm showing all walls to be 12"block,if we thicken the door wall it robs floor area or maks building bigger(comment?) I am forwarding this plan to the engineer to do preliminary structual ,won't go far tit floor size is agreed to. we are assembling the cabinet in the warehouse <110808134937-001.pdf> EFTA_R1_00255522 EFTA01857583
