To: jeevacationft il m' v i n mail.com] Cc: TOM MELNICK From: brice gordon Sent Tue 12/20/2011 7:21:27 PM Subject: Electric to top of hill and five palms five palms electric.xlsx attached estimate for power to top of hill and 5 palms 4 weeks lead time for Glidden portion I week for wire from PR 3 weeks work for toms crew wire prices are subject to change, transformers, switch gear etc are covered in Gliddens estimate LSJ would be responsible for digging trench, laying of conduit and pulling wire. Brice Gordon Little Saint James USVI Phone: EFTA_R1_00242256 EFTA01849862