To: Emad Hanna From: Jeffrey Epstein Sent Mon 7/27/2009 4:18:54 PM Subject: Re: Mechanical Building gary has to decide it ok On Mon, Jul 27, 2009 at 11:34 AM, Emad Hanna < wrote: Jeffrey, I just wanted you to be informed of the following: Gary Kerney has approved a payment of $ 9,241 to Kraus Manning for testing on the mechanical building. This puts this budget line item over budget by $ 7,771 and Gary also stated there will be an additional $ 12,009 of testing fees. So he is adding a change order for $ 19,771 bringing the total amount for testing to $ 29,771. If you're ok with all the above I will process this payment and adjust the working budget for the change order. Thank you Emad Hanna Project Controller HBRK Associates PO Box 400 EFTA_R1_00188984 EFTA01815765 New York, NY 10150 Ph Fax EFTA_R1_00186985 EFTA01815766