From: Jeevacation <jeevacation@gmail.com> Sent: Thursday, December 2, 2010 2:15 PM To: Emad Hanna Subject: Re: Courtyard Lights Ok Sorry for all the typos .Sent from my iPhone On Dec 2, 2010, at 9:02 AM, "Emad Hanna" wrote: Jeffrey, Just wanted to inform you the LED lights I was given to price out and purchase have a 4 to 7 week lead time to get them to LSJ and cost is around $ 4,800. So before I go ahead and order them I just wanted to let you know. Please advise if I should go ahead with this? Thank you Emad Hanna Project Controller HBRK Associates 301 East 66th St Suite 10F New York, NY 10065 Cell LSJ Office St. Thomas Office 1 EFTA_R1_00142348 EFTA01801434 NY Office Fa <mailt 2 EFTA_R1_00142349 EFTA01801435