New Engineering Building Pad Temp Enclosure/safety Material Handling Material Outside Vendor Labor Shipping Trucking Tax Equipment Rental 1500 Misc Expenses 1000 Layout/Survey Earthwork and Demo 1300 2000 Site Drawings Pest Control Site Dranage 1000 Pipes/Utilities 500 Concrete 9350 500 9500 2500 Vapor Barrier 200 Ties/Accessories/bolts 1500 Rebar 1400 Saw Cutting 250 Curing/Protection 300 Fine Grade 1000 Wood/Formwork 1200 5000 Fastners 400 Sub Totals 18100 3300 14500 4500 Total 40400 Note: Labor # is for outside labor only/ finish concrete crew Note: Rebar is for additional rebar Note; This is a basic pad No Utilities, septic sysyem, electrical, wall, or engineering yard work The pad will have 3 gray water drains. The pad will not have sanitary drains Includes min work on electrical vault EFTA01109771