From: Richard Kahn <:a> To: "jeffrey E." <jeevacation@grnail.com> Cc: Leighton Allenby Subject: Lutron Date: Tue, 18 Aug 2015 13:51:48 +0000 i spoke with Al and they were going to begin pulling the panels on 2nd, 1st and 4th floor tomorrow wednesday aug 19th they are ok to begin on monday aug 24th based on your upcoming visit since once that begins it will be a solid week of no lights new estimated date is sep 4th however they may need to do some minor tweaking week of sep 7th menvin sent 3 emails showing protection that has been laid (will send next) please advise if they should pull protection and if so on which floors thank you Richard Kahn HBRK Associates Inc. EFTA00848405