From: "Gary Kemey To: "Jeffrey Epstein" <*eevacation a mail.com> Cc: "Emad Hann Subject: concrete Date: Thu, 26 Aug 2010 20:20:30 +0000 Attachments: 100826153556-001.pdf Jeffrey/Emad When we had the conversation of the cost of the airplane hanger and I told you the slab would cost $350,000 and you questioned the cost of concrete,) said $300 to $400 a yard.The rule of thumb is concrete in place is about double the cost of the cost of just the concrete;ie steel,fonns,placement and finish. Apples to apples ,our cost to produce 4,000# concrete is $164.17 vs. St Thomas comcrete at $188.50 And if we use our produced stone our cost is $131.57(roads only) EFTA00758228