arrow_back Search

EFTA00655264

DOJ Epstein Files
folder Dataset 9 insert_drive_file EFTA00655264.pdf description PDF text_fields 154 words · 1.0k chars
open_in_new View original source

From: To: jeevacation@gmail.com CC: Subject: Gil update Date: Fri, 18 Mar 2011 15:11:55 +0000 just Gentlemen, The right gear is completed and will be shipped today. We should receive this by Monday. The left gear is in the machine shop, they have performed an NDT of the effected area and it appears there is enough material to remove the corrosion and remain within limits. They will proceed this weekend with the machining and check the remaining thickness again on Monday and get engineering involved for approval as well. There is still a good chance the corrosion is beyond acceptable limits. I should have an answer no later that Tuesday on this gear leg. Everything else is just about wrapped up. If you have any further questions, please feel free to contact me. Have a great weekend! Best Regards Jet Aviation St. Louis, Inc. Joe Allen Gulfstream Customer Support Manager an update from Midcoast: EFTA00655264