Construction Proposal August 5, 2015 Between the Owner: LSJ Little St. James Island St. Thomas, VI And the Contractor: Betteroads Asphalt LLC For the Project: LSJ Roadway/Pathway Drainage Measures Little St. James Island USVI SCOPE OF WORK: Excavate for and place 32 concrete swales with rip rap detention areas as shown on drawings entitled "Little St. James RV and Pedestrian Pathway Re-Surfacing Project" and dated September 18, 2014. Each proposed area contains the following; • Concrete Swale measuring 6ft. (W) x l2ft. (L) x 4in. (D) • Aggregate Base Pad measuring 6ft. (W) x I2ft. (L) x 3in. (D) • Rip Rap Detention Area measuring 8ft. (W) x 8ft. (W) x 6in. (D) TOTAL BASE PRICE: $42,062.40 LSJ Roadway/Pathway Drainage Measures August 5. 2015 I of 2 EFTA00608343 Project Totals: Name Road Drainage Measures Concrete swale Aggregate Base Pad Rip Rap Detention Area Company Overhead Percentage G rand Total Quantity Unit Cost Unit Total Cost 32 $855.00 32 $138.00 32 $150.00 Ea. $27,360.00 Ea. $4,416.00 Ea. $4,800.00 15.00% 50.00 Percent of Costs $5,486.40 $42,062.40 LSJ Roadway/Pathway Drainage Measures August 5, 2015 2 of 2 EFTA00608344